➤ Design, Planning, Consultancy, Erection, Installation, Testing & Commissioning of 100 MW Power Plant’s Overall Electrical Job including 132/11 kV Substation, Bay Extension at PGCB Grid Substation & 132 kV Transmission Line (1.2 KM).
Responsible for design and drawing of 132/11 kV substation earthing system, Cable raceway system, Switchyard layout, Electrical SLD for HV, MV & LV system, Bay extension design at PGCB Grid Substation, Existing Bus-Coupler shifting design, Clearance Diagram, Substation equipment’s footprint drawing, Transformer Oil Containment Pit Design, Protection system design, Switchgear & control room design. Sizing Calculation & Preparation of technical data sheet for LA, PT, CT, DS, CB, TX, Main bus (ACSR Conductor & AL tube) and DC Systems. Preparation of BOQ for Cables, Substation equipment, Gantry Structures, Clamp & Connectors. Design, drawing & installation of internal & external electrification, indoor & outdoor lighting and Lightning Protection System (LPS) for the entire plant by Active Air Terminal (Erico System 3000).