50 MW Shahjibazar Power Plant.
Position: Design & Supervision Engineer
Timeline: May 2017 to June 2017
Location: Shahjibazar, Sylhet, Bangladesh
Company: Energy Prima Ltd. - https://hosafgroup.com/energyprima.php

Main Project Features

➤ 40/50 MVA Transformer Erection, Installation, Oil Filtration, Cabling and Testing & Commissioning of Substation equipment’s of Bay-2.

Activities Performed

Responsible for the dismantling of burned substation equipment, including 30/35 MVA Power Transformer & connecting cables of Bay-2. After that, 40/50 MVA Power Transformer erection, installation, oil filtration, cable connection, and testing & commissioning of substation equipment are of Bay-2.